Does pharma's investment boom have a delivery problem?

Does pharma's investment boom have a delivery problem?
When investment plans meet delivery reality
The wider cost of uncertainty
Pharma is building delivery capability, but gaps remain
Three priorities for building greater certainty

Does pharma's investment boom have a delivery problem?

Pharma's investment boom is exposing a worrying confidence gap. Companies are committing billions to new manufacturing capacity, yet our Construction Certainty Index reveals that just 43% of pharma and life sciences leaders are very or completely confident of meeting project deadlines. Only 31% have the same confidence in staying on budget. With long-term capital commitments being made in an increasingly uncertain market, how can pharmaceutical leaders protect the value of their investments?

Worldwide demand for GLP-1 treatments is driving much of this growth. Biologics and advanced therapies are adding to demand. In the US, pharmaceutical tariffs are encouraging more domestic manufacturing investment.

Recent commitments show the scale of investment. In September 2026, Eli Lilly broke ground on a $6.5 billion manufacturing facility in Houston.1 It forms part of the company's wider US expansion programme. In Ireland, Novo Nordisk announced a €432 million investment to upgrade and expand its Athlone facility for oral GLP-1 medicines.2

These investments come amid global uncertainty. From geopolitical tension to energy price volatility, the shocks keep coming. Pharmaceutical facilities take years to plan, build and bring into use. During that time, costs can rise, supply chains can be disrupted and production delayed. Each change can put expected returns at risk.

“The investment decisions made today will shape manufacturing capacity for years. Yet the conditions in which those investments must be delivered can change dramatically. For pharmaceutical companies making major, long-term investments, resilience needs to be built into delivery from the outset. That means recognising risks earlier, understanding how they could affect the project and having the flexibility to respond before they become costly delays.”
— John Graham, Chief Growth & Collaboration Officer, Currie & Brown

1 Lilly breaks ground in Houston | Lilly Investors

2 Novo Nordisk announces more than 400 million euro expansion | Novo Nordisk

When investment plans meet delivery reality

76%

say material cost inflation has a high or very high impact on delivery

63%

say the same about supply chain disruption

45%

say uncertainty raised costs by more than 10% over the previous 12 months

Pharma's growth comes at a time when construction risks are harder to predict. What happens when rising costs, equipment delays and specialist labour shortages hit the same programme?

The effects can compound quickly. Higher costs change procurement plans. Supply chain problems force changes to construction sequencing. A lack of specialist skills raises costs and reduces the options available when conditions change.

The stakes are already high. Some 76% of pharma respondents to our recent Construction Certainty Index say material cost inflation has already had a high or very high impact on delivery. Almost two-thirds (63%) say the same about supply chain disruption.

A lack of skilled workers is also causing delays. Half of pharma respondents say skills shortages delayed at least a quarter of their construction projects in the past year. Other sectors are also competing for the same people and equipment. Data centres and semiconductor plants often need the same contractors, engineers and specialist resources. This is further limiting availability in some markets.

These factors carry a significant financial cost. According to the Index, 45% of pharma respondents say uncertainty raised costs by more than 10% across their construction projects over the past 12 months.

Timely, strategic intervention can significantly limit the impact of disruption. For example, when permitting difficulties and programme delays affected an upgrade to reagent-handling facilities at a US pharmaceutical site, the team revised construction sequencing, improved reporting and worked more closely with delivery partners. These measures saved more than $2.5 million and reduced the delay by a third.

The wider cost of uncertainty

Recovering construction time and cost is valuable. But delays to manufacturing capacity can have consequences far beyond the project itself.

Demand for new treatments is rising, while many patents are nearing expiry. This makes the timing of new manufacturing capacity a major business issue.

Our Construction Certainty Index highlights the wider implications for investment. Across all sectors, respondents estimate that 31% of potential projects have not started or progressed beyond planning because of uncertainty. This suggests that uncertainty can influence which investments move forward, as well as the cost of delivering them.

For pharmaceutical companies, these decisions need to be considered across the entire investment portfolio. A delay at one facility may hold up a product launch or limit capacity elsewhere. Bringing one project forward may also draw funds or staff away from another.

Understanding these links helps leaders judge which delays carry the greatest commercial cost, and where action would protect the most value.

Steve Townsend, Global Head of Pharmaceuticals and Life Sciences at Currie & Brown, has managed major capital programmes from both the client and consultancy sides.

“We work with a global life sciences company managing around 100 projects at any one time. With investment on that scale, you need to understand how projects affect one another and where delays could have the greatest commercial impact.

For example, if several projects need the same specialist resources, which should take priority? The answer depends on when that capacity is needed and what a delay would mean for the wider business. Having that portfolio-wide view helps make better decisions and protect the value of the investment.”

Pharma is building delivery capability, but gaps remain

The Construction Certainty Index shows differences in how firms prepare for uncertainty.

The research identified five markers of maturity linked to greater confidence and better project outcomes:

Greater use of AI to identify, monitor or mitigate risk

Digital tools influencing project or asset decisions

Data analytics recognised as effective in reducing uncertainty

Sustainability embedded in project delivery

Investment in skills or training

The findings suggest that pharma is making progress. Across all sectors, 32% of respondents demonstrated at least four of these five markers. In pharma and life sciences, the figure was 41%.

The difference in delivery confidence is striking:

What does stronger capability look like in practice? Eli Lilly's manufacturing facility in Concord, North Carolina, provides one example.3 The facility progressed from groundbreaking to US Food and Drug Administration approval in just 30 months. Integrated teams, standardised designs, modular construction and digital twin testing all contributed to its accelerated delivery. Digital testing allowed the team to identify and address issues before equipment arrived on site.

Across the sector, investment in these capabilities is increasing:

But technology delivers greater value when it supports informed decisions and helps teams respond to change.

Clear governance and shared information can help project teams adapt to changing requirements while maintaining control of cost and programme. We saw this on a 21,000m² laboratory and office project in Germany. As the client's research needs evolved, we used structured change control to assess proposals against cost, programme and operational requirements. A shared digital building model improved coordination and helped identify potential clashes early. The project maintained key milestones and achieved savings against the approved budget. The digital approach was also adopted across the client's wider development programme.

Despite this progress, the Index reveals a significant gap between adopting technology and embedding it into delivery. While 54% of pharma respondents say AI and digital integration influence several delivery stages or are central to their approach, only 18% say they are central to how assets are designed, built and operated.

Access to reliable information remains a barrier. Almost half (47%) report limited access to real-time data, while 41% struggle to integrate information from different sources.

These gaps have consequences beyond individual projects. Without connected information, leaders may struggle to see how delays, resource pressures or changing requirements on one project could affect investments elsewhere. The challenge is to turn growing digital capability into the clarity and control needed to manage risk across the entire portfolio.


3 2026 ISPE Facility of the Year Awards (FOYA) Category Winner for Operations – Project Execution | ISPE

Three priorities for building greater certainty

So how can pharma organisations turn stronger capabilities into more reliable delivery? Three priorities stand out.

1

Build flexibility into capital portfolio planning

Plans must account for changes in product demand, patent expiry and manufacturing needs. Each facility should be assessed for its impact on the wider production network.

Review where capacity is needed and how priorities could change. Which facilities must be ready for a critical launch? Which could adapt if demand shifts? Test the consequences of bringing forward, delaying or changing investments elsewhere in the portfolio.

The sooner these options are clear, the easier it becomes to respond when conditions change.

2

Plan around the availability of skills and resources

Access to specialist expertise can determine whether a project is achievable. Resource availability must shape plans from the start.

Assess the skills needed at each stage of delivery. Check their availability in the proposed location, including competition from other major projects. Consider whether expertise from related industries could fill gaps. Modular and offsite construction may also help reduce demand for scarce resources.

These choices can affect where and how facilities are built. They also help teams set realistic delivery dates.

3

Use data and technology to anticipate risk and make decisions earlier

The Index shows rising use of AI and data analytics in pharma. The priority is to turn that investment into more accurate forecasts and better-informed decisions.

Reliable cost benchmarks, market intelligence and connected project and procurement data can help teams spot risks early. They can also show how problems may interact across a portfolio.

Teams can test different scenarios, from rising material costs to longer equipment lead times. This helps them assess the impact and identify alternatives. AI can support this work, provided the data is reliable and experienced people can act on the findings.

Decision-makers will then have a clearer basis for choosing when and where to act.

New manufacturing capacity creates value when it is ready at the right time. Seeing risks early, and keeping options open across the portfolio, gives organisations a better chance of achieving that.

Talk to our experts

Build greater certainty into your next investment.

Let's explore what it takes to turn your investment plans into successful delivery.

Build greater certainty into your next investment.

Start a conversation with us about your delivery challenges.

Talk to our experts